Service level Agreement for High End Maintenance Teams As per the Industry Practices
Service Level Agreement
| ||||||
S no.
|
Perameter
|
Response time
|
Diagnosis time
|
Resolution time
|
Remarks
| |
1
|
Electrical power availability (Transformer / HT Panels / DG Sets / Main power control center)
| |||||
Grid failure-Provide standby DG Power
|
Immediate
|
Immediate
|
25 seconds
| |||
DG Set Tripping
|
Immediate
|
Immediate
|
10 minutes
| |||
System Uptime
|
99.95%
|
Allowable downtime annually: 263 Minutes
| ||||
DG Repairs- first level maintenance- Replacement of spares involved
|
10 mins
|
10 mins
|
4 hours
|
Power should be restored with stand-by arrangement in 10 mins. Should insure compliance of SLAs/resolution times agreed by OEM
| ||
DG Repair- require OEM support
|
10 mins
|
30 mins
|
8 hours
| |||
DG- Major repairs- require replacement of parts with OEM support
|
30 mins
|
8 hrs
|
3 days
| |||
Transformer/ HT switch gear/ HT Panels-first level maintenance- Replacement of spares involved
|
10 mins
|
10 mins
|
4 hours
| |||
Transformer/ HT switch gear/ HT Panels- require OEM support
|
10 mins
|
30 mins
|
8 hours
| |||
Transformer/ HT switch gear/ HT Panels-Major repairs- require replacement of parts with OEM support
|
30 mins
|
8 hrs
|
3 days
| |||
2
|
UPS System
| |||||
UPS System Tripping/ Restoration
|
Immediate
|
Immediate
|
10 mins
| |||
System Uptime
|
99.99%
|
Allowable downtime annually: 53 Minutes
| ||||
UPS System Repairs- first level maintenance- Replacement of spares involved
|
10 mins
|
10 mins
|
4 hours
|
Power should be restored with stand-by arrangement in 10 mins. Should insure compliance of SLAs/resolution times agreed by OEM
| ||
UPS System Repair- require OEM support
|
10 mins
|
30 mins
|
8 hours
| |||
UPS System- Major repairs- require replacement of parts with OEM support
|
30 mins
|
8 hrs
|
3 days
| |||
Battery replacement- require OEM Support
|
10 mins
|
30 mins
|
8 hours
| |||
Battery bank replacement
|
30 mins
|
8 hrs
|
3 days
| |||
3
|
Electrical-LT System
| |||||
LT Panel/ DB/MCB Tripping/ Restoration
|
Immediate
|
Immediate
|
10 minutes
| |||
System Uptime
|
99.95%
|
Allowable downtime annually: 263 Minutes
| ||||
LT Panel/ DB/MCB Repairs- first level maintenance- Replacement of spares involved
|
10 mins
|
20 mins
|
1 hours
|
Power should be restored with stand-by arrangement in 10 mins. Should insure compliance of SLAs/resolution times agreed by OEM
| ||
LT Panel/ DB/MCB Repair- require OEM support
|
10 mins
|
30 mins
|
8 hours
| |||
LT Panel/ DB/MCB- Major repairs- require replacement of parts with OEM support
|
30 mins
|
8 hrs
|
3 days
| |||
4
|
HVAC and PAC system
| |||||
Tripping of equipement
|
Immediate
|
Immediate
|
10 minutes
| |||
System Uptime
|
99.95%
|
Allowable downtime annually: 263 Minutes
| ||||
Equipement Repairs- first level maintenance- Replacement of spares involved
|
10 mins
|
20 mins
|
1 hours
|
Stand by system should be restored with stand-by arrangement in 10 mins. Should insure compliance of SLAs/resolution times agreed by OEM
| ||
Equipement Repair- require OEM support
|
10 mins
|
30 mins
|
8 hours
| |||
Equipement- Major repairs- require replacement of parts with OEM support
|
30 mins
|
8 hrs
|
3 days
| |||
5
|
Fire Alarm System
| |||||
Fire fighting system
| ||||||
Fire alarm acknowledgement
|
Immediate
|
Immediate
|
2 mins.
| |||
Alarm resolution time
|
Immediate
|
Immediate
|
5 mins.
| |||
System Uptime
|
99.99%
|
Allowable downtime annually: 53 Minutes
| ||||
Arresting the water leakage in the system
|
Immediate
|
Immediate
|
30 mins
| |||
Equipement Repairs- first level maintenance- Replacement of spares involved
|
10 mins
|
10 mins
|
30 mins
|
Stand by system should be restored with stand-by arrangement in 10 mins. Should insure compliance of SLAs/resolution times agreed by OEM
| ||
Equipement Repair- require OEM support
|
10 mins
|
30 mins
|
8 hours
| |||
Equipement- Major repairs- require replacement of parts with OEM support
|
30 mins
|
8 hrs
|
3 days
| |||
Checking of fire extinguishers
|
Monthly
|
4 hrs
|
1 day
|
Minor repairs
| ||
Refilling of fire extinguishers
|
Yearly
|
8 hrs
|
6 days
|
Stand by extinguishers should be in place in 1 hr
| ||
6
|
Elevators
| |||||
Elevator failure/ rescue operation
|
Immediate
|
Immediate
|
10 mins.
| |||
System Uptime
|
99.95%
|
Allowable downtime annually: 263 Minutes
| ||||
Equipement Repairs- first level maintenance- Replacement of spares involved
|
10 mins
|
10 mins
|
30 mins
|
Stand by system should be restored with stand-by arrangement in 10 mins. Should insure compliance of SLAs/resolution times agreed by OEM
| ||
Equipement Repair- require OEM support
|
10 mins
|
30 mins
|
8 hours
| |||
Equipement- Major repairs- require replacement of parts with OEM support
|
30 mins
|
8 hrs
|
3 days
| |||
7
|
General complaints
|
These complaints include low priority complaints like faulty light fixture,temp setting, leakage in water lines, general cleaning, and doors problem etc
| ||||
Electrical
|
Immediate
|
10 minutes
|
30 minutes
| |||
AC Temperature
|
Immediate
|
10 minutes
|
30 minutes
| |||
Plumbing
|
Immediate
|
10 minutes
|
30 minutes
|